Tuesday, July 27, 2021
PLASTERING RATE PER SQ.FT
Friday, July 16, 2021
Cost Control Techniques in Construction
Construction is a major industry spreading rapidly with the increasing population of this world. History shows the rate of gradual increase in prices of Building materials, Skilled Labors, and Machinery used in construction.
The concept of Supply and demand in
Economics helps us to understand fluctuation and raises in the cost of Construction
that cannot be controlled as population
is getting increase alarmingly.
What we can do to control the cost
of construction is future cost control with present prices, so effectively we
can control the cost of construction
adopting the following techniques.
1- Design of construction
Avoid over design and unnecessary
use of materials and construction size ,it has been observed that mostly
engineers do over designing using extra spaces and materials which causes high
and unnecessary costs that is due to the lack of good and precise engineering knowledge.
2- Wastage of Labor and Machinery
It is has been observed that
Managers and supervisors cannot manage scheduled usage of labor and machinery
which causes low productivity and high unbearable cost burdens in construction.
Avoiding such problems Design
feasible planning for labor and machinery usage and control every activity by
motivation and routine supervision check and balance.
3- Appointment of skilled Team at Construction
Sites
Skilled people do more productivity
and precise work and also can control wastages very effectively so appoint
people on a merit system.
4- Proper Estimation and Execution
Estimate materials and labor
expenses properly and execute construction activities according to the
limitations of Estimated budgets.
5-Preparation of Detailed Drawing before Estimation.
Detailed drawing along with detailed specification should be prepared before estimation so that construction cost
may be assessed accurately and also size, the number of construction elements may
be controlled that will cause control of cost.
6-Maintaining Inventory very soon after
Estimation.
As we know market prices keep uplifting so
purchase all material soon after the estimation and also do agreements with
Labor contractors and give them time frames.
Follow times lines of project so
that labor contractor can manage his teams accordingly avoiding labor and time
failures.
7-Avoid Changing in Design.
Do not change construction design
when it is designed in the initial stages because when the design has changed the cost
also gets the change.
This Blog contains supporting images which are
property of Google only.
What is Organization in Management
It is a Business group where two or more persons work together to accomplish a target or a common purpose.
we can see many organizations around
us working for some special goal or purpose as Colleges, Factories, Schools, Government
Offices.
The concept of People, Purpose, Process, and POLCA
is very important to understand the organization.
People
who works in an organization
Purpose
for which people work together
Process
is Set of specific activities specially designed by managers to complete
different tasks for the attainment of organizational goals.
In the concept of POLCA Organization Process stands on four supports of management
which are as follows.
1- Planning
Planning is shaping the organizational
goals and the means for achieving them in allowable Limitations.
2-Organizing
The organizing is deciding where decisions will be made, who will do what jobs, who will work for whom, and tasks in given timelines and standards.
3-Leading
Leading is inspiring and motivating
workers to work hard to get organizational goals.
4-Controlling
Controlling is monitoring progress
towards goal achievement and taking corrective action to fulfill deficiencies.
In the modern era, Good managers adopt
two styles of controlling.
A- assure themselves to perform
these functions well.
B-
Managers are altering the way they execute these functions, thinking of themselves
more like mentors, coaches, team leaders, or internal consultants. They work
with anyone who can help them complete their goals rather than only following
the chain of command.
They ask others to contribute in
making decisions and share information with others to maximize the progress of
attaining the goals.
5-Assurance
Assurance is formulation and direction
in the quality assurance programs and
policies, and also struggle hard to bring the most excellent in the
organization.
Thursday, July 15, 2021
How to Calculate shear force in Simply Supported Beam
Shear Force is the algebraic sum of all vertical forces acting on either side of the point on the beam. Shear force is to shear off the beam along with the point where it is acting.
1- Calculate Reactions
we will use Minus (-) Sign for
downward forces (Loads) and Positive (+) Signs for Upward Forces (Reactions or
Supports)
Taking Moment at Reaction "A"
+RAx0 - (1200x60)-(3000x20)-(4000x47)+(RBx60)
-(72000)-(60000)-(188000)+RBx60
RB = 320000/60 =
5333.333 Lbs
We know that (RA+RB) = Total Load
RA+RB = (3000+4000)+(1200x60)
RA+RB = 79000 Lbs_________Eq.1
Putting value of RB in Eq.1
RA+(5333.333) = 79000 Lbs_________Eq.1
RA = 73666.667 Lbs
Now Calculating Shear forces at
different points
Shear force at point "a" due to reaction A = +73666.667 Lbs
Shear force at point "b" = 73666.667-(1200x20)-(3000)
SF due to UDL =73666.667-(24000)= +49666.667 Lbs
SF due to Point Load =49666.667-(3000)= +46666.667 Lbs
Shear force at point "c" = +46666.667-(1200x27)-(4000)
SF due to UDL =+46666.667-(1200x27)= +14266.667
Lbs
SF due to Point Load =+14266.667-(4000) = +10266.667
Lbs
Shear force at point "d" = +10266.667-(1200x13)+(5333.333)
SF due to UDL = +10266.667-(1200x13) = -
5333.333
SF due to Reaction RB = -5333.333+5333.333 =0
This Blog contains supporting images which are
property of Google only.
Wednesday, July 14, 2021
Function of Shear Wall
This is a structural member of RCC structures to provide lateral stability against horizontal forces caused by Wind pressures and Earthquakes.
Shapes of Shear Wall.
Shear walls are designed in different shapes using Reinforced cement concrete materials which produce resistance against the horizontal forces that act to over-turn the structures.
Placement of Shear Walls.
Shear walls are placed at three
locations
1- On the edges of the building.
2-Inner side of Building on various
locations.
3-On the Center of High rise buildings.
The function of Shear Wall.
There are
various useful functions of shear walls.
1-Shear Wall
provides resistance against self-load of structure, movement loading, and
resultant loading such as uplift loads acting on shear walls.
2-Shear Wall
holds gravity lines of all areas of the building that can create extra stresses during movements and may damage nonstructural elements in the building.
3-Shear wall
keeps stiffness of junctions (on column and beams) within the design limit.
4-Shear wall
provides protection in lateral displacement and sway of the building.
5-Shear wall
provides safe structural movement under earthquake and wind pressures.
The Calculation for Loading Function.
Let's have a
calculation session on design of shear walls as shown in this building plan.
Suppose the
each span is 20 ft and slab design load is 300 Pound/Sq.Ft.(Including weight of
walls ).
Total Load
of one floor = (80'x40'x300)= 960000
Pounds
Factored load =(960000x1.5) =1440000 Pounds
Now whole
Plan will be divided 5 Parts as showing (Area
1=800 Sft), (Area 2, =600 Sft + 600 Sft ),(Area 3,= 300 Sft+300 Sft).
Now load can
be calculated for each shear force
Load on Area
1 Shear Wall =(800x1440000)/(40x80) =360000 Pounds
Load on Area
2 Shear wall = (600x1440000)/(40x80)=270000 Pounds
Load on Area
3 Shear Wall =(300x1440000)/(40x80) =135000 Pounds
Uniformly Distributed Load
Calculation
Considering
shear wall as a beam between two junctions of the slab and beams vertical height is
12 ft.
UDL For Area 1, Shear Wall = 360000/12= 30,000
Pound/Ft
UDL For Area 2, Shear Wall = 270000/12= 22,500 Pound/Ft
UDL For Area 1, Shear Wall = 135000/12= 11,250 Pound/Ft
Moment of
Area 1, Shear Wall=( w.L.L.x12) /8=
= 30000x12x12x12/8=6,480,000 (Lbs-Inch)
Moment of
Area 2, Shear Wall=( w.L.L.x12) /8=
= 22500x12x12x12/8=4,860,000 (Lbs-Inch)
Moment of
Area 3, Shear Wall=( w.L.L.x12) /8=
= 11250x12x12x12/8=2,430,000 (Lbs-Inch)
Moment of Resistance = 250xbxd1^2 ................ EQ.1
we knows
that M.r = Moment
Putting values into Eq.1 for Area 1 Shear Wall
Longer side in Inches =10x12= 120 Inch
Shorter side
in Inches =8x12= 96 Inch.
(6,480,000/2)
(Lbs-Inch) = 250x 120xd1^2
d1 = 7.34
say 7.5" Adding cover 1" on both faces = 9.5"
Repeating
for Shorter Side
(6,480,000/2)
(Lbs-Inch) = 250x 96 xd1^2
d1= 11.61
Say 12" Adding cover of 1" at
both faces = 14"
Maximum size of wall thickness is
14" so adopting this
Area of
Steel = M/Fst.Lever Arm
6,480,000/2x20000x.75x12
=18 Sq.Inch
For Spacing Using
1 " Dia Bars = Area of Bar x width /Area of Steel
Spacing =(0.785x96)/18 =4.18 say 4" C/C (Vertical Bars)
Now
Calculating the stirrups spacing
Spacing of
1/2" Dia bar =Area of 6-Leg Stirrups x Fst x Lever Arm/Shear Force
6x0.302x20000x0.75x12/(30000x12x.5x.5)
=3.5" C/c
Shear Wall Area 2
Longer side in Inches =15x12= 180 Inch
(4,860,000 (Lbs-Inch)= 250x 180xd1^2
d1 = 10.39 say
10.5" Adding cover 1" on both faces = 12.5" (Shear wall Thickness)
Area of
Steel = M/Fst.Lever Arm
4,860,000 /20000x.75x10.5=
30.85 Sq.Inch
For Spacing Using
1 " Dia Bars = Area of Bar x width /Area of Steel
Spacing =(.785x180)/30.85 =4.5 "c/c (Vertical Bars)
Now
Calculating the stirrups spacing
Spacing of 1/2
" Dia bar =Area of 12-Leg Stirrups x Fst x Lever Arm/Shear Force
=
12x.302 x20000x0.75x10.5/(22500x12x.5) =4.25" C/c
Shear Wall Area 3
Longer side in Inches =8x12"= 96 Inch
2,430,000 (Lbs-Inch)= 250x 96xd1^2
d1 = 10 Adding cover 1" on both faces = 12" (Shear Wall Thickness)
Area of
Steel = M/Fst.Lever Arm
2,430,000 /20000x.75x10=
16.20 Sq.Inch
For Spacing Using
1 " Dia Bars = Area of Bar x width /Area of Steel
Spacing =(.785x96)/16.2=4.5 "c/c (Vertical
Bars)
Now
Calculating the stirrups spacing
Spacing of 1/2
" Dia bar =Area of 6-Leg Stirrups x Fst x Lever Arm/Shear Force
=
6x.302 x20000x0.75x10/(11,250 x12x.5) =4" C/c
Monday, July 12, 2021
Why Curing of concrete is Important.
The curing process is keeping the
concrete moist awaiting the safe hydration of concrete is complete and strength
is accomplished. Curing of concrete should start on soon after
initial setting time of concrete and should be continued up to 28 days to
attain maximum strength of concrete.
Good Curing of concrete results in
the following strength.
Comparative
Strength of Ordinary (Portable) Cement concrete at various ages |
|
Curing Time |
Compressive Strength |
3-Days |
40% |
7-Days |
65% |
14-Days |
90% |
28-Days |
99% |
3-Months |
115% |
6-Months |
120% |
1-Year |
130% |
Why Curing is Important.
1-Curing is required to avoid dryness
of concrete during setting and hardening of cement that is only possible with
effective hydration of cement, Now how hydration of cement will be effective,
it's only possible when mixing water will remain in concrete during
setting time period of concrete which is 28-days.
If curing is not started after
placing the concrete it will produce only 50% of the total designed compressive
strength in concrete.
2-Curing ensures the safe processing
for the attainment of strength in concrete structures and also helps in speedy construction
practices.
For Example, Concrete Structure avails
90 % strength in 14-Days and mostly engineers remove formworks after 14-days
because structures can afford to hold their self loads after 14-days. The self-load of structures remains around 50% of the total designed load so when concrete
avails its 90 % strength it provides easy and safe decision to remove the formwork
without any hesitation.
3-Curing can raise the strength of
concrete up to 130% which is the guarantee of long life and durability of concrete
in less budgeting, so it is easy to design the structures for 100 years with
effective curing of concretes.
4- Curing helps to attain high and
required strength in concrete which helps to avoid faulty constructions and
also finally provides a safe and
reliable structures.
Curing Methods
1- Shading.
In this method, concrete is covered to
avoid evaporation from sun rays.
2-Ponding.
This method is used only for
horizontal surfaces of slabs and concrete roads but require a lot of water.
3-Spraying of
Water.
This method involves the sprinkling of water on concrete surfaces to keep moist surfaces but this is difficult as requires periodic showering of water.
4-Membrane Curing.
In this method of curing a chemical
coating /Using some membrane is provided on the surface of the concrete to avoid
evaporation of concrete water.
5-Steam Curing/
Hot water Curing.
Curing with Steam and hot water is
sometimes adopted to gain rapid development
in the strength of concrete. This process of curing is best for the construction of
Pre-Cast Structures.
6-Covering.
This is a broadly used technique of curing, mainly for structural concrete. The uncovered surface of the concrete is prohibited from drying out by casing it with a hessian cloth or canvas cloth.
Sunday, July 11, 2021
How to design a simply supported beam manually
Suppose we have a beam whose span is 30 Ft , and a Point Load "F"=10000 Pounds, which includes weight of beam and imposed load.
In this case we are going to design a
RCC Beam using Load Factor Theory in following steps.
1-Find out Support or Reactions
Left and Right Support = F/2= 5000 Pounds
In given symmetrical loading case
both reactions are equal
2-Find out Max shear force = Load /2
= 10000/2 =5000 Pounds
Shear force at support = +5000 Pounds
Shear force at Mid = +5000 + (-10000) = -5000 Pounds
3-Max Bending Moment at Center of Beam = Reaction
x L/2
Max MB= 5000x (30/2)x12= 900000 Pound-Inch--------1
4-Moment of Resistance = K.b.d1^2----------------EQ.2
5-b (width of beam ) = (Span x12)/30
=12"
Value of "K" = 250 in Load Factor Method using (1000-20000)
Concrete
Where fc =1000 PSI and Fs = 20000 PSI
We know that Moment of Resistance
=Bending Moment so comparing both
equations EQ----1 AND EQ-----2
6- 900000 = 250x12xd1^2
d1 (Effective Depth) = 17.33 inch Say
17.5"
7-
Area of Steel in Tension zone = BM /(FstxLever Arm)
Ast =900000/(20000x0.75/17.5)= 3.42 Sq.in
No of bars according to 3/4" dia bars = Ast/area of one bar =8 nos.
8-Area of steel in compression zone =(B.M - M.r)/fst.Lever
Arm
=((900000-(250x12x17.5^2))/20000x
0.75x17.5
=(900000-918750)/20000x0.75x17.5=
- (0.07)
Use (4+4) nos
of 3/4" dia bars and 2 no of 1/2" dia bar at top sides.
Use 3/8" dia bar stirrups 2-Leg @ 10 "
c/c
Minus sign shows that the M.r value is greater than the applied value of B.m so no need of Asc (Area of steel in compression zone ), Only two steel bars of 1/2" dia bars are enough to hold stirrups.
Use (4+4) nos of 3/4" dia bars
and 2 no of 1/2" dia bar at top sides.
9- Spacing of stirrups = Aw.Fw.Lever
arm/(Shear Force)
=(0.22x18000x0.75x17.5)
/5000 = 10" C/c
Here Aw = Area of 2 leg stirrup bars
Fw = Permissible value of Tensile stress of stirrups
Overall depth of beam = Effective
depth+ 2 concrete covers
concrete cover = 1"
Concrete ratio =1:2:4
Factor of safety in Fc = 3000/1000=3
Times (considering compressive strength of concrete)
The factor of safety in Fst= 60000/20000=3 Times
(considering Tensile strength of Steel).
This Blog contains supporting images which are
property of Google only.
Popular Posts
-
The building design is a very complex and scientific process due to higher required safety for its residents so following procedures shoul...
-
Water is used for the production of many elements in the construction industry as water is the key ingredient being mixed with cement to f...
-
There is a famous phrase that the world has become a global village because of the Internet and computer technology. The concept of global...
-
Auditorium Design Concept The auditorium is a big room building facilitated with sitting arrangements for Audience and Stage for p...
-
Corrosion in RCC Element is a natural process that takes place when the steel bars within reinforced concrete structures become rusty. Sci...
-
Wind is a mass of air that travels from high-pressure zones to low-pressure zones having low and high velocities which exert pressures on ...
-
The construction industry has become very expansive because of the high prices of Labor and Materials. Civil Engineers use different desig...
-
The curing process is keeping the concrete moist awaiting the safe hydration of concrete is complete and strength is accomplished. Curing...
-
Slump is vertical settlement of the concrete after the mould has been withdrawn and the vertical difference between height of mould and th...
-
Time management is life management because the second name of time is life and there is no life if there is no time. Time management is pla...