Tuesday, July 27, 2021

PLASTERING RATES PER m2

 

PART A ) MATERIAL COST 
PART B ) LABOR COST 
We will calculate plastering cost considering material cost and labor cost and will not include other expenses as Cost of working tools ,Labor Accommodations,  Labor transportations, Scaffolding cost Shifting of mortar material in high rise buildings because there are variations which depends on nature of projects with different leads and lifts.
In ideal conditions 1 -Mason and 1 Helpers along with 2  Labor for shifting and mixing of mortar can easily do 14-Sq.m of plastering with complete perfection. After years of experience it has been known that "A" Class  Mason can do 14-Sq.m of plastering in 8 Hours and "B" Class mason can do 9.30 Sq.m  of plastering in 8 Hours.

CALCULATION FOR PLASTERING MATERIALS 
WET VOLUME = AREA OF PLASTERING XTHICKNESS OF PLASTER
DRY VOLUME = WET VOLUME X 1.27 
1.27 IS DRYING FACTOR 
1- QUANTITY OF CEMENT IN BAGS = 
(CEMENT BY PART x  DRY Volume) / (Sum of ratio x Vol of one bag of cement)
2- QUANTITY OF SAND IN Cu.m  = 
(SAND BY PART x  DRY Volume) / (Sum of ratio)
3- QUANTITY OF WATER  IN LITERS  = 
NOS OF CEMENT BAGS x 50 x 2 x14 days of curing=  Liters of water

Daily Material Quantities when "A" Class Masons working

S NO

DESCRIPTION

QUANTITY IN (Sqm)

CEMENT in Bags

Sand in Cu.m

WATER in Liters

1

Cement sand plastering (1:1) 13 mm thick

14

3.226

0.11

4516

2

Cement sand plastering (1:2) 13 mm thick

14

2.151

0.15

3011

3

Cement sand plastering (1:3) 13 mm thick

14

1.613

0.17

2258

4

Cement sand plastering (1:4) 13 mm thick

14

1.290

0.18

1806

5

Cement sand plastering (1:5) 13 mm thick

14

1.075

0.19

1505



Costing of Materials

S NO

Description

Materials

Quantity

Unit Price

Cost of Materials

1

Cement sand plastering (1:1) 13 mm thick

CEMENT in Bags

3.226

620

2000.00

Sand in Cu.m

0.11

1412.8

159.51

WATER in Liters

4516

0.15

677.42

MATERIAL COST

2836.92

2

Cement sand plastering (1:2) 13 mm thick

CEMENT in Bags

2.151

620

1333.33

Sand in Cu.m

0.15

1412.8

212.68

WATER in Liters

3011

0.15

451.61

MATERIAL COST

1997.62

3

Cement sand plastering (1:3) 13 mm thick

CEMENT in Bags

1.613

620

1000.00

Sand in Cu.m

0.17

1412.8

239.26

WATER in Liters

2258

0.15

338.71

MATERIAL COST

1577.97

4

Cement sand plastering (1:4) 13 mm thick

CEMENT in Bags

1.29

620

800.00

Sand in Cu.m

0.18

1412.8

255.21

WATER in Liters

1806

0.15

270.97

MATERIAL COST

1326.18

5

Cement sand plastering (1:5) 13 mm thick

CEMENT in Bags

1.075

620

666.67

Sand in Cu.m

0.19

1412.8

265.85

WATER in Liters

1505

0.15

225.81

MATERIAL COST

1158.32



LABOR COST

S NO

Description

PLASTERING AREA in Sq.m

MASONS@ 1200 Rs/Day

LABORS/HELPERS@ 800Rs/Day

Labor Cost

1

Cement sand plastering (1:1) 13 mm thick

14

1

3

3600

2

Cement sand plastering (1:2) 13 mm thick

14

1

3

3600

3

Cement sand plastering (1:3) 13 mm thick

14

1

3

3600

4

Cement sand plastering (1:4) 13 mm thick

14

1

3

3600

5

Cement sand plastering (1:5) 13 mm thick

14

1

3

3600




FINAL RATE SUMMARY

S NO

Description

1-(Plastering Area) in Sq.m

2-(Labor Cost)

3-(Material Cost)

Rate per Sq.m =(2+3)/1

1

Cement sand plastering (1:1) 13 mm thick

14

3600

2836.92

459.78

2

Cement sand plastering (1:2) 13 mm thick

14

3600

1997.62

399.83

3

Cement sand plastering (1:3) 13 mm thick

14

3600

1577.97

369.86

4

Cement sand plastering (1:4) 13 mm thick

14

3600

1326.18

351.87

5

Cement sand plastering (1:5) 13 mm thick

14

3600

1158.32

339.88

Note :- In above working unit price of materials and labors can be changed according to any location in the world.