Thursday, July 1, 2021

Building construction process from start to finish


The building design is a very complex and scientific process due to higher required safety for its residents so following procedures should be kept in mind during the design of buildings, I am submitting an exemplary drawing to narrate every procedure with visible references.

 Need of Building and Architectural Design.

                Residential Building Plan (Fig no.1)

First of all, there should be a need for a building according to user requirements, the user should estimate the number of residents being accommodated in that building.The building should be perfectly designed and planned according to the user's requirements. After deciding on futuristic needs we should draw a detailed Architectural Drawing having plans, Elevations, sectional details, Finishing materials, Levels of floors and roof, Electric and Water supply designs, Door, Window designs, painting details, for building construction and this drawing should be approved by the local government as per standards and practices.
At this stage, many points should be kept in mind which are as follows.

SIZING AND CAPACITY OF BUILDING

The building design is a very complex and scientific process due to higher required safety for its residents so following procedures should be kept in mind during the design of buildings.

Sizing of rooms, Size of Doors & windows, Height of Building, Size of Overhead water tank, Size of the Main gate, Size of sewer pipes, Size of Manholes, Size of Septic tanks, Slope of Ramp in front of the main gate, Size of Porch, Size of Bath Rooms, Size of Store, Location of Stairs, Number of Lights, Fans, Air Conditioning, Number of Ventilators, Height of Parapet wall, Size of Cantilevers, Size of Open to sky s. Size of Kitchen Cabinets, Kitchen Counters and sizing of Kitchen Sinks, Location of Shower, water closets, Floor Traps, Bib cocks, Hand Basins, Toilet Showers, Position of light plugs, Switch Boards, Distribution boards, Size of Electric Cables, Size of Sewer pipes, Etc.

Design of Sub-Structure and Super-Structure.

Design of Sub-Structure.

Building structures should be designed according to the availability of materials from the local market because this is the main reason to control building costs.

The most lower structure generally called foundation or Sub-structure should be designed considering the bearing capacity of Ground-level where the foundation will be placed. Normally it ranges from .5 Ton/Sft to 1.5 Ton/ Sft.

Let's say after testing we availed Bearing Capacity 1Ton/Sft and now we have to design our foundation structure considering BC of 1 Ton/Sft.

Take the biggest square panel slab from a given plan that is Drawing room whose size is (14'x14') where wall thickness is 9" having a good class of bricks, now we will add one wall thickness in size of slab panel and our effective span will be 14.75'x14.75'

Now we have to do some simple calculations

Roughly Thickness of slab for two-way slab panel = Effective Span/35 =14.75x12x1/35= 5" so slab thickness will be 5 " for the entire slab.

Now the width of foundation = (Weight of Structure) /(Wall Perimeter x Bearing Capacity)

Now we have only the value of bearing capacity which is 1 Ton/Sft

Weight of structure = Weight  of Walls + Weight of slabs +Weight of Foundation+ Imposed loads (Live Loads + Dead Loads)+ Load of Finishing

Weight of Walls = Perimeter of all walls x Height of walls x Thickness of walls x Density of Brickwork

Note:- Brickwork density = 120 Lbs/Cft

But in case of solid block, walls density will be 140 Lbs/ Cft

Perimeter of Walls = 50.75+50.75+30.75+30.75+30.75+30.75+4.75+10+4.75+11.75+14.75+10+5.75

=286.25 Rft  (Dimensions are calculated from given plan)

Weight of load bearing walls = (286.25x12x.75x120)     =309150 Pounds

Weight of Load-bearing walls in Tons =309150/2240 = 138.01 Tons

Weight of Slabs =Length x Width x Thickness of slab x Density of RCC

Dimensions as per Fig no.1 = 50'x30'x5/12'x150 Lbs/Cft=93750 Lbs/2240= 41.85 Tons

Imposed loads (Live Loads + Dead Loads) =40 Lbs /Sft

Total Imposed Load = 50x30x40 PSF=    60000 LBS=60000/2240=26.78 Tons

Load of Finishing= Weight of plaster +Weight of Roof Waterproofing

Weight of Plaster =2 Times of perimeter of walls x Height x Thickness x Density

=2x286.25'x12x.06x50 Lbs/ Cft=20610 Pounds/2240=9.20 Tons

Weight of Roof Water Proofing=50x30x 50 Psf=75000 Lbs/2240= 33.48 Tons

NOW putting values in following Formula as also mentioned above

Weight of structure = Weight  of Walls + Weight of slabs +Weight of Foundation+ Imposed loads (Live Loads + Dead Loads)+ Load of Finishing

=(138.01 Tons+41.85 Tons+ 26.78 Tons+9.20 Tons+33.48 Tons) x 1.25 times= 311.65 Tons Say 312 Tons

Note 25 % of total structure weight added for the weight of foundations

Factored Load = 312 Tonx 1.5 Times = 468 Tons

Now width of foundation = (Weight of Structure) /(Perimeter x Bearing Capacity)

To calculate width of foundation putt values in the above formula

=468 /(286.25 x 1 )= 1.69 ft

We have stepped footing in foundation so we can use 22.5" wide stepped layer in Brick Work then 18 "then 13.5" wide and then 9" Bedding Concrete of 30" wide may be laid under the brickwork.



1-We will use section (b) for load-bearing walls as shown in the above figure adopting B= 30 inches c=3.75"

2-PCC (1:3:6)        The thickness of step 1- as shown "B" = 30" and thickness "d"= 4" 

3-Brick Work (1:5)  Width =22.5"  Depth= 6"

4- Brick Work (1:5)  Width =18"  Depth= 6"

5- Brick Work (1:5)  Width =13.5"  Depth= 6"

6- Brick Work (1:5)  Width =9"  Depth= Up to Roof slab bottom

7 -Depth of Excavation = 22"

Section (a) named as simple footing will be used for boundary wall having 9" thickness.

Concluding the above calculations I will narrate the foundation in the wording of specifications as follows

1- Excavation in all types of soils except rock and including lead of 50 ft and lift of 4 ft for surplus soil, Average Size of excavation trench will be (30"x22") complete in all aspects.

2-Provide and Lay Pcc (1:3:6) 4" Thickness using Good class of cement, sand and crush completely in all aspects.

3-Brick Work (1:5) Using Good class of Bricks and cement sand mortar

4-DPC (9" wide and 2" deep ) will be provided on FFL Using a (1:2:4) ratio having three coats of hot bitumen and 2 layers of polythene sheet

Trenches will be filled with surplus soil and will be compacted up to 100 % modified proctor test and the lower area under flooring will be filled with sandy soils and will be compacted layer by layer up to 100 % Modified Proctor value.

 

Design of Super-Structure.

Super-structure mainly includes load-bearing walls, Slabs, Lintel and beams, Overhead Water tank, and Columns.

Design justification of 9" thick walls is very simple here as the wall bears 50% of brick strength and the brick strength for good bricks has been the standard compressive value of 1800 PSI, It means we will use 900 PSI for or brick walls.

The top area of all walls = Perimeter of walls x Width of walls

                                     = 286.25 x.75 x144= 30915 Sq.Inch

The load-bearing capacity of walls = 30915 Sq.Inchx900=27823500 Pounds /2240 =12421 Ton x .33=4099 Ton (This is the overall bearable loading value of load-bearing walls whereas our total load is 468 Ton which is only 11.41 % of the total bearable load. 

Design of RCC Slab (1:2:4) 5"  thick

Roughly Thickness of slab for two-way slab panel = Effective Span/35 =14.75x12x1/35= 5" so slab thickness will be 5 " for the entire slab.

Now we will formulate the following equation to find out the thickness of the slab and required Steel spacing for the slab.

Moment of Resistance= K.b.d1.d1

Where K is factor value in Elastic Theory Design method

b= is taken as 12 " which is constant for all slabs when adopting Foot Pound System.

d1= Effective Depth

As we know that MR (Moment of resistance) = Bending Moment

So Bending Moment of square slabs  = wxlxlx12x1/16  --------------EQ.no A

w= 130 PSF for residential buildings

l=14.75 ft as effective span

so putting values in EQ.no A

Bending Moment= 130X14.75^2X12X1/16= 21212 lbs-in

Comparing  MR (moment of resistance) = Bending Moment

K.b.d1.d1=21212 lbs-in

184X12Xd1^2=21212 lbs-in

d1= 3.04 inches  say 3.5 " adding 2 concrete covers of 0.75"+0.75"=5"

so overall depth of slab is 5"

Now we will calculate the area of steel

As= B.M/Fst .la --------------Eq .no. B

La=.857d1

Fst =20000

Putting values in Eq .no. B

As=21212 lbs-in/20,000x0.857x3.5" = 0.353 Sq.in of steel is needed in each foot of slab.

Spacing of bars using 1/2" dia bars =Area of 1/2" dia bar x 12 x1/As=

0.196 12 x1/0.353= 6.66 say1/2" dia bars @ 6.5 Inch Center /Center will be used  in both ways of 5" thick slab having ratio of (1:2:4)Concrete.

use 50 % of As in negative reinforcement so the area of negative reinforcement =

.50x0.353=0.1765 Sq.in

Using 3/8" dia bars ,spacing =0.11x12/.1765= 7.47 "

According to British RCC code spacing should not be more than 1.75 times of Effective depth (d1) of slab =so 3.5"x1.76= 6.125 say Use 3/8" dia bars @ 6 inch and place holding bars % 12-inch center /center.

Note:- Other slabs will be calculated with the same methodology or maybe roughly calculated comparing other spans with the Larger span which is designed as above.

British Engineering design contains Load Factor and Elastic Theory Method which contains Factor of the safety of 3 Times.

 Construction Procedure with all activities. 

1- Leveling of Ground Using Tractor with Blade.

2-Layout of Building.

3-Excavation in form of trenches.

4-Compaction  in trenches.

5-Provide and Lay PCC (1:3:6) in the trench using mixing machine and labor.

6-Provide and Lay Brick Work(1:5) using Good Materials and Labor.

7-Vertical DPC from Foundation Concrete to Finish Floor levels

8-Back filling of trenches, Area under flooring, and 100 % modified proctor compaction in layers not exceeding more than 6" thickness.

9-Provide and Lay Horizontal DPC on all walls at Finish Floor Levels.

10-Provide and lay PCC sub base for flooring except for washrooms and kitchens.

11-Provide and Lay Brickwork and Lintels in Super Structure.

12-Scaffolding and shuttering of Slab.

13-Steel fixing in slabs and beams.

14-Supply and Fixing of Electric conduits in Roof slab.

15-Pouring of Rcc (1:2:4) Slab 5" thick.

16-Removal of shuttering after curing time normally after 14 days because concrete reaches up to 90 % of its strength and can support its own weight very easily but slab should not be loaded within 28 days from pouring time.

17- Provide and Lay Brick Work of Parapet wall

18-Supply and Fixing of Electric Conduits and Boxes in walls including grooving and placing of pipes in walls and finally filling of grooves with Mortar.

19- Supply and Fixing of water Supply in walls including grooving and placing of pipes in walls and finally filling of grooves with Mortar.

20-Provide and Lay sewerage pipes at the inner and outer side of the building along with the construction of Manholes and galley traps, and connection with main sewer line complete in all aspects. The sewer line will include P-traps, Floor Traps, bends, elbows, Unions, sockets as per requirements.

21-Plastering of walls including fixing of Door and Window Frames.

22-Construction of Boundary wall including Fixing of the main gate with concrete Pillars complete in all aspects.

23-Construction of Flooring including fixing of tiles on floors and fixing of tiles on bath room's walls up to door heights.

24-Supply and Fixing of Wooden cabinets, Doors, Windows (Aluminum made), Stair Railings Etc.

25-Fixing of Bath Accessory Set including Wc,s  , Wash Hand Basins or Vanities along with fixing of marble slabs, Showers, and Bib Cocks.

26-Painting of Doors, Grills, and railing.

27-Provide and lay roof waterproofing along with the construction of overhead water tanks and fixing of rainwater drain pipes.

28-Distemper at inner walls and Weather shield at the outer side of walls with three coats complete in all aspects.

29-Fixing of Electric Accessories including Lights,Fans, Ac,s ,  Distribution boards, Earthling systems, Main doorbell, Smoke detectors, Exhaust Fans, Complete in all aspects.

30-Construction of Ramp for car porch in front of Main Gate.

31- False Ceiling in Rooms

32-Construction of Floor beds including concrete work, Brick Work, Plastering and Supply, and laying of sweet soil for plantation.

Possibilities of Construction Activities Quantities done by Manpower and Machines.



One Tractor can Level 100 ft x 100 ft area with maximum volume of soil per day 5000 Cubic. Feet.

Hourly Fueling may be calculated with following formulas

Maximum Hourly Fuel Consumption = Horse Power of Machine x 0.12=Liters

Minimum Hourly Fuel Consumption = Horse Power of Machine x 0.10=Liters


 

Surveyor is Professional who is responsible for LayOut and Leveling process in Construction Industries. Machines and tools used in Surveying are Leveling Instruments, Theodolite, Total Station, Measuring Tapes, Etc.

In building Construction One Surveyor Along with helper can easily Control process of Layouts and Leveling in area of 15000 Sft /Day.



                Shuttering for Pcc under the stepped footing of building 

One carpenter and Helper can do Shuttering to prepare the area of 150 Sft.

2 Masons along with 15 Labors can do  1000 Cft.


                        For the construction of RCC slabs thickness from 5" to 7" 


One Carpenter and two labors can do 80 Sft of Shuttering in One day

One Steel Fixing and one helper can do 500 Kgs of steel in 8 hours.

3 Masons along with 18 Labors can do  800 Cft .in 8 hours using a mixing machine, Tower Lift in construction of slabs for single storied buildings.

     


                                   Brick Work using cement-sand mortars.     

One Mason and 2 Helpers Can complete 70 Cft of brickwork in 8 hours, And Half day of 1 Carpenter and 1 Helper will be consumed to make formwork.



                                                            Cement Plaster.

One Mason Along with 2 Labors Can complete 130 Sft of plaster And Half day of 1 Carpenter and 1 Helper will be consumed to make formwork.


                                                       Tile Floors 

One Mason and 2 Labors can complete Fixing of tiles for the area of 100 Sft in 8 hours.


                                                             Distemper

One Painter and 2 Labors can complete an Area of 450 Sft in 8 Hours With the Application of 3 coats.


                                                        Weather Shield

One Painter and 2 Labors can complete an Area of 400 Sft in 8 Hours With the Application of 3 coats.

Formwork workers will be provided as per the height of the structure.



                            Wall Grooving and Water Supply pipes 

2 Plumber and 2 Helpers can do grooving and water supply piping for 1 Wash Room /Day


                                                    Bath Accessories    

2 Plumber and 2 Helpers can Complete 1 wash Room in 4 Days including all accessories of washroom.


                                        Electric works in Domestic buildings 

             1 Electrician and 1 Helper can complete 20 Sft (Covered Area) in 8 Hours


                                  Woodworks in Domestic buildings 

1 carpenter and 1 helper can complete 7 Sft in 8 Hours.

Above working can be considered for the construction of residential buildings in ideal circumstances as these are experienced observations and practicable having small resources.






































































































Saturday, June 26, 2021

Auditorium Design Concept

 

Auditorium Design Concept   

The auditorium is a big room building facilitated with sitting arrangements for Audience and Stage for performers for presentation, acting, and motivations.

The uses of Auditoriums are several depending upon the type of requirement of the public as it maybe a Theatre, Cinema, Conference Room, Meeting room, Assembly Hall, Award showroom etc.

Shape of Auditoriums

Auditoriums  may be constructed in any form but mostly it is constructed in rectangular and sector of circles or Curves considering availability of the land size and orientation of the building.






Size of Auditoriums

The most important thing in the design of the Auditorium is sizing to facilitate Audience and performers avoiding all possible problems.

1- Size of sitting area in Curvy rows

The seating capacity for 1 person should be 6 Sft to 7 Sft which includes a minimum passage area of 5 Sft for 1 person.

2- Size of sitting area in Straight rows

The seating capacity for 1 person should be 6 Sft to 7 Sft and the minimum area of    5 Sft for a person should be added for passages.

3- Volume Capacity for 1 Person and Height of Auditorium.

volume required for each person in the auditorium should be 124 Cft to 160 Cft with a minimum height of 20 Feet and Maximum Height can be calculated using nominal volume and area required for one Individual.

 4- Seating Alignment.

Seating alignment should be staggered in a way so that spectator in any line is not sighting over the head of an individual sitting in front of him.

5- Head Room

Minimum head rooms under the landings and cantilever portions should not be less than 7 ft.

6- Area of Ventilators and Door , Windows.

The area of Doors, Windows, Ventilators adjacent to in an open space  should be 15% (In case of Air Conditioning of Hall)  and 20% of Total Floor Area in case of Fans and Exhausts fans ventilation.

 7- Size and spacing of chairs /Seats.

The width of seats should be 19" to 21" and the back to back distance of seats should be 3 ft to 3'-6" and the crossing passage in front of chairs should be 1'-6" to 2ft for traveling in between the chairs back and front. Seating the angle should not be less than 65 degrees.

8- Level of Stage.

The level of the stage should be 3'-3" higher than the lowest level of flooring in front of first-line from the stage.

9- Arrangements to avoid resonance.

Sound absorbing material should be used on walls, round walls should be avoided in Auditoriums. Thick carpeting also helps to control echo problems.

10- Design of stairs.

Minimum width of the stair should not be less than 6'-0" and the minimum size of the tread and rise should be 12"x6".

 11-Position of Screen

The position of the screen should be fitted in a way that the angle eyesight of the person sitting in a front line from the top of the screen may not be more than 34 degrees.

12-Structural stability of Auditorium

Structure of Auditorium building should be designed by competent designers and good construction practices should be adopted to complete the building.

 

 

 




Technical Education

 



Technical Education

Education having special techniques and knowledge using different tools to produce engineering products is called Technical Education. Engineers can not complete any engineering project without technical people having special technical knowledge and experience.



Engineering Fields



Before more discussion about technical Education we should know about different engineering fields where technical education can be utilized.

So there are some main engineering fields utilize technical people.  

1-Civil Engineering,

2-Mechanical Engineering,

 3-Electrical Engineering,

4-Instrumentation Engineering,

5- Mechatronics Engineering,

6-Architecture Engineering,

7- Metallurgical Engineering,

8- Refrigeration Engineering,

9- Chemical Engineering,

10- Computer Engineering,

11- Environmental Engineering,

12-Biomedical Engineering,

13- Aerospace Engineering,

14-Automotive Engineering,

15- Electronics Engineering,

16- Robotics Engineering,

17- Agricultural Engineering,

18-Paper Engineering

19-Petroleum Engineering,

20-Geological Engineering

21-Marine Engineering

22- Nuclear Engineering

23-Minning Engineering

24- Geomatics Engineering,

Perhaps there is no business that can be done without using technical knowledge and technical resources. In the industrial production process different skilled persons works with their knowledge and experience, Engineers provide design ideas using their scientific knowledge and Technicians provide middle-level supervision to artisans to make the products.

Technical skills involve engineering implementations using the proper methodology, and engineering standards. Technically skilled people are backbone of any industry they are result oriented people and works for business profitability and futuristic growth of industries.

Artisan is a skilled worker who uses their hands and tools to make different machines and products, they work efficiently under the supervision of technically educated people.

Technical people (Technicians and Technologists) behaves like a bridge between designers (Engineers) and Artisans. Technical Individuals  transforms engineering and scientific knowledge to uneducated  Artisans and ensures the accuracy and required  standards in production.

Who are Technical People?

After matriculation technical people passed through three-year diploma which is called (DAE) Diploma of Associate Engineer and this diploma course is recognized worldwide. There is further educational degree after DAE whose name is B-Tech or BS in Technology and holding this level degree any individual can work as Engineer.

Why Technical Education is needed

It is observed that people having scientific education and even only engineering education cannot perform supervision because of having less Technological skills.

The nations who promoted Technological people with respect and equality are more progressive instead of those countries that only gave respect to white-collar engineers who are habitual to sit in offices and only doing documentation.

Many progressive countries like Australia Technicians and Technologists are treated on both levels like their Engineering councils accept them as an engineer and also as a Technologist, I believe Australia is the best country to consider the level of equality and respect for the people who build the nations.

Technical Education contributes 80 % to 90 % in Any Engineering Project.

In any industry it has been observed that Technical people contribute 80 -90 % of their time in completion of any project or product because they are the only people who can perform basic engineering activities more concisely and perfectly rather than of engineers who only holds scientific and theoretic knowledge.

Technical people hold keys for each activity so that is the reason they are also called key supervisors.

In civil engineering it is observed that most of the surveying jobs are completed by technical people as they are physically strong and fit to work in any weather. Engineers work on these survey reports and design the products having all solutions for the problems confronted by society.  

Engineer can't be a good Technologist But A Technologist can be a Good Engineer.




It is observed that Technologists are more effective in performing engineering activities but due to lack of technical skills engineers cannot perform most of the field works. Industries have promotional policies for technologists after years of experience and time. Technologists can be better managers than engineers because they know a lot of root-level knowledge and the working capacity of artisans.

Technical Education for growth of nations.

Technical  education should be promoted globally to provide more employability and economic sustainability to poor nations. I think specially designed schools should be established to produce Technical people and only technical people should be promoted to engineering degrees to supervise and design the industries more effectively.

Technical people should be facilitated with online low-cost degree programs because it has been observed that they are treated to work only on junior positions and engineering lobbies are enjoying higher salaries only because of their favorable job policies in many countries.

Morality and equality are bookish words that are only reserved for a special class of wealthy people to become an Engineer or Doctor standing on the heads of Technical people.







































































Monday, June 7, 2021

Global Warming and Establishment of Modern Villages


There is a famous phrase that the world has become a global village because of the Internet and computer technology. The concept of globalization has provided platforms for fast-tracked businesses and enterprises for the growth of humanity but on another hand, the world is losing nature and causing global warming.

It is only because of the modern lifestyle of people ignoring natural style of living. The world has been designing by a division having many features as the present Land area is 148,429,000 Sq. Km  Present Sea Area  241,197,125  Sq. Km so it means there is a natural balance for the existence of the earth. Everything has been designed according to designed proportions balancing the existence of this world.

Human life should be designed to support and to save natural resources, the huge budgets which are expensed on defense should be expensed on the welfare of this world.

Presently 56 % Population is living in urban areas and the remaining is living in villages, towns, and jungles. Our focus should be the development of village areas to promote a nature-friendly environment.  



Global warming is dangerous as causing pollutions and damaging our natural resources like melting of glaciers, reducing of jungles and trees, low production of oxygen, damage of ozone layer. We should take measures to adopt village life containing all nature-friendly projects like Plantation, vegetation, raising of birds and all types of framings. 

Now it is the time to gather all countries of the world through a reliable Platform to take measures for global warming because global warming is the enemy of humanity.

All countries should take part in the establishment of Modern villages according to their particular Populations and atmospheric requirements.

The concept of modern villages

Modern villages should be designed in every country on this planet having all facilities like employment, education, health facilities, Food and Pure Water, Small level industries as needed to stop immigrations of people to urban areas as causing massive level pollutions and global warming.


Economic values of Modern villages

Village creates people having healthy minds and hardworking individuals and a major part of urban the population consists of villages- people who have been migrated to cities because of fewer facilities and employment opportunities in villages.

The agricultural industries are not promoted because agricultural products having less pricing and no attention from all Governments in the world because industrial the mafia of urbanization is controlling Political and Government levels to promote urban areas only. These mafias are doing business by selling their products on high prices and getting rapid expansions in promotions of urbanizations whereas the villagers having products with low pricing strategies are migrating to cities.

An alarming fact can be seen on economic levels that villagers are producing agricultural products and shifting to cities because markets exist in cities controlled by the agents of governments and middlemen, this is why village side populations are decreasing.

Government should establish markets in villages and rates should be declared by village controlling bodies with profitability.



  Education in Villages

School , Colleges and Universities should be in villages to educate people for modern farming with degrees in agriculture Industries.

Agricultural and Environmental Ministries should be established by Governments to collect fund to maintain and promote villages life.

Promotional Arrangements for Farming

It has been observed that half of the population living in village areas don't have their own agricultural lands and because of the economic crisis these families shifted to urban areas.

Governments Should lease allotment of agricultural lands to such families so that more low cost manpower can be engaged and also a facility of earning may be produced for poor villagers.

Small Industries and Technical Colleges for Villagers 


  Technical and Small Industrial Journey 


Establishment of small industries like handicrafts, flour mills, Agriculture Machinery workshops will be helpful for village economies.

Technical colleges will produce technical hands to contribute to the village economy and to support village life infrastructures.     

Special Design of Houses 




Special houses should be constructed with mud and soil because construction with cement is a big source of Carbon Dioxide. Mud houses contain very little amount of cement concrete so such construction should be promoted in villages.

Water Management and Sewerage System  



Quality of underground water is becoming brackish because of unplanned and faulty sewerage the system so a good engineering methodology should be adopted to overcome these problems. 

 Growing Forests as Source of Rain


 Forests are great source of rain so the growing of trees will help to reduce pollution and raining will help to grow green lands. Green lands and forests provide fresh air and a lot of oxygen.



Unity to Protect this World.

This is time to save our world and save humanity from massive unstoppable destruction. We have to care for and respect natural resources and all creations on this globe. Countries should join hands together to make a safety wall against global warming, if we keep ourselves sleeping against this destruction everything will be finished and nothing will stop this from happening.

Protect this world considering it as its own home.



It is the duty of every nation on this earth to protect and support this Planet for coming Generations and Life.













Posts

What is afflux in Hydraulics

Popular Posts